Clarence Ave water main project starts Monday, June 22

The City will be installing new water mains on Clarence Avenue between 8th Street and College Drive starting Monday, June 22 at 7:00 a.m. This work is expected to take  about 5 months to complete, weather permitting and barring any unforeseen circumstances.  
Detours will be in place guiding motorists around the construction zone while this work is underway. 

Phase 1– Clarence Avenue from 8th  Street East to 12th  Street East – beginning June 22 for approximately  4  weeks.    
Phase 2– Clarence Avenue from 12th Street East to Colony Street – approximately 5 weeks. 
Phase 3 – Clarence Avenue from Colony Street to College Drive – approximately 6 weeks.    
Phase 4 – Temperance Street from Munroe Avenue to Wiggins Avenue – approximately  7 weeks. 

For more information on the Clarence Avenue Water Main Replacement Project, please visit saskatoon.ca/watermain